Project Management Software is a Tool, Not the Answer to Project Planning & Control

Updated: May 04, 2010

Select a Sound Project Management Methodology

All projects have three major elements that need to be controlled in order for a project to be successful. Those elements are Time, Cost, and Quality. Time is measured by using a schedule, cost is measured by using a budget, and quality is measured by using specifications. Projects are only successful if they are completed on-time, within budget, and to specifications. If the project management system you have selected does not take into consideration all three of these elements then you will have a difficult time planning and controlling your project through its completion. Your project deadline, budget, and quality constraints will require you to make trade-offs in these three variables. A sound project management approach creates an opportunity to make better decisions about those trade-offs earlier in the process and thereby increases the probability of success.

Select Tools that Support the Chosen Methodology

There are many project management software packages currently available in the market today. Finding a software tool that quickly provides the information needed to analyze and make decisions for your project is not a simple task. While many project management tools are good for planning the initial schedule, sometimes it can be difficult to update the schedule, change resource allocations, modify activity durations or change precedence relationships. Select a tool that has a friendly user interface, easily allows plan changes and supports your chosen project management methodology.

The Planning Process

A good planning process is made up of three distinct steps:

  1. Define the Project
  2. Develop an Initial Project Plan
  3. Compress the Schedule and Develop a Baseline Plan

Defining the project is the first step towards having a successful project outcome. During this step the project manager is selected and the sponsor(s) of the project is interviewed to determine exactly what he/she is expecting the project team to deliver. Once the project has been defined by the sponsor(s), the project team is assembled to develop the project charter. The charter should contain a short background statement, the expected deliverables, the project objectives, the list of the project team and sponsors, a list of key dates, and any assumptions, risks, and constraints that the project team can identify. In addition, the project charter should also contain the time-cost trade-off rate. This is defined as the cost to the organization if the project is finished late or the benefit if finished early. The time-cost trade-off rate is used to make cost effective decisions for compression of the project plan. Once the team is in agreement about the project's scope, key personnel requirements, major constraints, assumptions, and risks, those items should then be presented to stakeholders for approval. By completing this process up-front, the project team will have a clearly defined (and understood) set of deliverables and an agreed-upon direction prior to making the investment in developing the project plan.The initial project plan is developed by the project team around the deliverables identified in the charter. The deliverables are broken down into work tasks (activities) through the development of a work breakdown structure. Once this is complete, the team needs to identify the task owners, durations and the precedence relationships. The precedence relationships are developed and documented using a network diagram. After the network diagram is developed, the project plan is entered in to the selected project management software for validation and schedule compression. Upon completion of the project plan compression and validation, a baseline of the plan is saved. The baseline plan is used to measure variance as the project is moved into the control mode.

The Control Process

The Control Process is the most important part of managing a project once a good plan has been developed. All projects should be updated on a regular basis, typically, every one to two weeks. The main objectives of project control are to:

  1. Gain an objective indication of the status of the project and key milestone dates
  2. Keep team members focused on the project and their activities
  3. Uncover and resolve any schedule-related problems
  4. Update the schedule to reflect the most current information about the project

The first step in the control process is to collect activity status information from the team members. The project plan should then be updated and the remaining activities should be rescheduled. The plan is then compared against the baseline plan and the variance is analyzed. If necessary, based on the update, the plan may need to be recompressed to meet the project deadline/key dates. The recompression is typically done with the project team. After the schedule has been recompressed, all team members need to reconfirm that they can meet the near term commitments for their assigned tasks. A project status report is then developed and distributed to the management and project team members. In some cases, a formal control meeting is held to communicate the update results directly to management and the project team members.

Featured Research
  • Are You Using These 5 VoIP Features?

    In large part, the success of your business depends on the strength and reliability of your team’s many communication networks—this includes your Voice over Internet Protocol system (VoIP). more

  • Video Conferencing Best Practices

    Video conferencing is quickly becoming one of the most important communication channels for both small and big businesses. As more businesses turn to this technology, expectations about the experience are also rising. It’s not enough to just offer video conferencing as a communication method. You also need to meet minimum audio and visual standards, and there’s even proper etiquette to consider. more

  • 10 Contact Center Myths Busted

    For most forward-thinking companies, the use of contact center software is on the rise. That said, in spite of contact center software’s sudden rise in popularity, a number of myths have begun to take shape. more

  • Go Mobile and Increase Employee Productivity

    The Bring Your Own Device (BYOD) and Voice over Internet Protocol (VoIP) tech trends now allow people to work whenever, wherever, and however they want—mobility makes it happen. more

  • [Infographic] How to Select a Phone System in 10 Steps

    Choosing the perfect phone system for your business is no small task …. Depending on the size of your company, the industry in which you work, and the specific needs your phone system will be required to meet, any number of solutions could get the job done. more